Jomtien Road construction expected to last until April of next year, expect delays

The construction currently being undertaken on Jomtien 2nd Road, which started June 6, is scheduled to finish on April 1, 2020.


Pattaya City hired Chokdee Engineer Products Co., Ltd. and Thai Tong Lee Co., Ltd. to reinforce the concrete surface and install rainwater drain pipes, as well as upgrade traffic signs and street lights to TISI standards.

Pattaya’s deputy city manager, Sutham Khetpetch, took a team of officials out to the construction site Oct. 21 to check on the progress. They found it to be about 15% complete.

Sutham said the contractors have been instructed to continue to work 24 hours a day, Monday through Thursday, but must shut down for the weekend starting at 5pm on Fridays. At that time, they must open the road to traffic and ensure machinery and materials are out of the way in a safe place to avoid accidents.

Source: Daily Mail

Subscribe
Adam Judd
Mr. Adam Judd is the Co-owner of TPN Media since December 2017. He is originally from Washington D.C., America, but has also lived in Dallas, Sarasota, and Portsmouth. His background is in retail sales, HR, and operations management, and has written about news and Thailand for many years. He has lived in Pattaya for over nine years as a full-time resident, is well known locally and been visiting the country as a regular visitor for over a decade. His full contact information, including office contact information, can be found on our Contact Us page below. Stories please e-mail Editor@ThePattayanews.com About Us: https://thepattayanews.com/about-us/ Contact Us: https://thepattayanews.com/contact-us/